Planning a House Extension in Dublin: Architect, Builder or Certifier First?
Who does what on a Dublin extension, and how to check a builder yourself. General information, not professional advice.
The short answer. If you already have drawings, a builder can quote from them and you are ready to go. If you do not, you need someone to produce them before any builder can give you a real price: an architect or architectural technologist for the design and the planning application if there is one, and a structural engineer for the steel and the foundations. Over 40 square metres you also need to decide who certifies the build. The order is design, then engineer, then price, then build; skipping the first two does not save money, it moves the cost to the end of the job where it is larger. This page is general information, not legal or professional advice.
Who Does What
The architect or architectural technologist designs the extension, produces the drawings a builder prices from, prepares and lodges the planning application if one is needed, and can administer the contract and inspect the work while it is being built. An architect is registered with the RIAI; an architectural technologist is a different, usually cheaper, profession that produces drawings to the same standard for straightforward domestic work. Either can do a rear extension well. For a two-storey extension, an unusual site or a protected structure, an architect's design input tends to pay for itself.
The structural engineer calculates the steel beam over the opening between the old house and the new room, the foundations, and anything that changes how the existing house carries its load. Almost every kitchen extension needs one, because almost every kitchen extension opens up the back wall.
The builder prices the drawings, builds what is on them, and coordinates the trades: groundworks, blockwork, roof, glazing, first and second fix electrics and plumbing, plastering and finishes. A builder is not a designer, and a builder who offers to "sort the drawings" is usually going to sub-contract them.
The Assigned Certifier, on extensions over 40 m², is a registered architect, engineer or building surveyor who inspects the work against the Building Regulations and signs the certificate of compliance on completion. This is a separate appointment from the designer, although it is often the same person.
You. The homeowner is the client under the Building Control Regulations, and on an extension over 40 m² the homeowner either appoints the certifier or signs the opt-out declaration. The decisions on scope, finish and budget are yours, and so is the contingency.
What a Builder Needs to Quote Properly
A builder can give you a rough figure from a conversation. A builder cannot give you a price you can hold them to without:
- Scaled plan and elevation drawings showing the size, the roof, the openings and how the extension meets the existing house.
- A structural engineer's design for the beam and the foundations, or at least a note that one is being commissioned, so the steel is not a provisional sum.
- A specification of the finish level: floor, glazing, doors, kitchen if there is one, heating, lighting. Two builders pricing the same drawings to different specifications will be thousands apart and neither is wrong.
- The planning position: exempt, applied for, or granted. Our extension planning permission guide sets out the rules as they stand since July 2026.
- Site information that affects the price: where the drains run, whether the ground has been built on before, access for a mini-digger, where the neighbours' boundaries sit.
If you go to builders with none of this, the quotes you get back are estimates dressed as quotes, and the difference appears as extras later. Getting drawings first costs money; it is the money that makes every later number real.
Building Control: Commencement Notices and Certification
Building control is separate from planning. Every extension must comply with the Building Regulations whether or not it needed planning permission. What changes at 40 square metres, the building-control threshold, is how that compliance is documented.
Under 40 m², the extension is built to the regulations without a statutory certification process. Over 40 m², a Commencement Notice goes to the building control authority through the Building Control Management System before work starts, and you choose between two routes:
- Statutory certification. You appoint an Assigned Certifier, the design is certified as compliant before work starts, the certifier inspects during the build, and a Certificate of Compliance on Completion is lodged at the end. This is the full route the 2014 regulations introduced.
- Opt-out. For a single house or an extension over 40 m², the owner may lodge a Commencement Notice with a declaration of intention to opt out of statutory certification. The obligation to comply with the Building Regulations does not go away; what goes away is the certified paperwork. Some lenders, insurers and future buyers will ask why there is no completion certificate, so the opt-out is a decision to take with advice, not a shortcut.
Since the July 2026 planning change, an extension between 41 and 45 m² is the odd case: no planning application, but a Commencement Notice and a certification decision. If you are designing to the limit, put both in the plan.
CIRI: the Builders' Register
The Construction Industry Register Ireland is the register of building contractors run by the Construction Industry Federation. It has operated on a voluntary basis for years, and the Regulation of Providers of Building Works Act 2022 is putting it on a statutory footing, category by category, starting with the builders of multi-unit housing. For most builders doing one-off domestic extensions, registration is still voluntary at the time of writing.
What that means for you: a CIRI listing is a positive sign, because a registered firm has been assessed and carries the insurance the register requires. The absence of a listing is not, on its own, evidence of anything, because most domestic builders are not yet required to be on it. Treat it as one check among several, not the check.
How Long It Takes
A realistic Dublin timeline for a single-storey rear extension, from first meeting to moving the furniture back in:
- Design and drawings: four to eight weeks, longer if the design goes through several rounds.
- Planning, if needed: the council has eight weeks to decide from a valid application, and a request for further information adds four more. Allow twelve weeks and be pleased if it is eight. Exempt extensions skip this entirely.
- Engineering and tender: two to four weeks to get the structural design done and three or four builders to price it.
- Lead time to start: the good builders in Dublin are booked months ahead. Two to four months from accepting a quote to breaking ground is normal.
- The build: ten to sixteen weeks for a single-storey extension of ordinary size, longer for two storeys or for a kitchen fit-out that runs after the shell is finished.
Add it up and a project that starts as an idea in January is often a finished room by the autumn. Starting the drawings early is how you control the calendar.
Contracts, Stage Payments and Your Rights
Get it in writing. A written contract that references the drawings and the specification, states the price, sets out the stage payments and names a completion date is the single most protective document in the whole project. The RIAI publishes domestic building contracts that architects use routinely; for smaller jobs a clear written quotation that covers the same points will do.
Stage payments, never a large deposit. A reasonable pattern is a modest sum on signing to secure the start date, then payments tied to milestones: foundations, walls to roof level, roof on and watertight, first fix, second fix, completion. Each payment follows work you can see. A builder asking for a large proportion of the price before starting is asking you to fund their cash flow, and if they do not come back you have no room and no money.
Retention. Holding back a small percentage of the final payment for a defects period is standard in construction contracts and worth asking for.
Variations in writing. Extras are where extension budgets go wrong. Agree that any change to the scope is priced and confirmed in writing before it is built.
Your consumer rights. Building work for a homeowner is a consumer contract, and the Consumer Rights Act 2022 sets the standard the work has to meet. Where a contract is agreed in your home rather than at the builder's premises, consumer law also provides a short cooling-off period after signing. The Competition and Consumer Protection Commission publishes plain guidance on both; check the current position there rather than relying on this page.
How to Check a Builder Yourself
We pass enquiries to a building contractor. We do not inspect their work or vouch for them, and we would rather say that plainly than imply otherwise. So here is how to check any builder, including the one we introduce you to:
- Ask for their public liability and employer's liability insurance certificates, and look at the dates and the cover level.
- Ask for two recent extensions you can see from the road, and one you can visit, and ask the owners how the job went and how the extras were handled.
- Look them up. The Companies Registration Office for a limited company, CIRI if they say they are registered, the planning register for jobs they say they built.
- Get the price in writing against the drawings, with the specification attached, and compare quotes on scope before comparing them on the total.
- Never pay a large sum up front, and never pay in cash for the sake of a discount that disappears with your rights.
A builder who is comfortable with all five is a builder you can probably work with.
This page is general information about how extension projects usually run in Dublin. It is not legal, financial or professional advice, and it does not describe any particular builder. Your architect, engineer, solicitor and the CCPC are the people to confirm the points that matter for your project.
Ready to get a price against your drawings, or want a builder's view before you commission them?